2018 Report on James Webb Space Telescope (JWST): Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap

Nonfiction, Science & Nature, Science, Physics, Astronomy, Astrophysics & Space Science
Cover of the book 2018 Report on James Webb Space Telescope (JWST): Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap by Progressive Management, Progressive Management
View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart
Author: Progressive Management ISBN: 9781370563555
Publisher: Progressive Management Publication: March 1, 2018
Imprint: Smashwords Edition Language: English
Author: Progressive Management
ISBN: 9781370563555
Publisher: Progressive Management
Publication: March 1, 2018
Imprint: Smashwords Edition
Language: English

JWST, a large, deployable telescope intended to be the successor to the Hubble Space Telescope, is one of NASA's most complex and expensive projects, at an anticipated cost of $8.8 billion. Congress set an $8 billion JWST development cost cap in 2011, and the remaining $837 million is for its operations costs. JWST is intended to revolutionize our understanding of star and planet formation and advance the search for the origins of our universe. With significant integration and testing planned for the remaining period until launch, the JWST project will still need to address many challenges during the remainder of integration and testing.

In 2017, the National Aeronautics and Space Administration's (NASA) James Webb Space Telescope (JWST) project delayed its launch readiness date by at least 5 months, and further delays are likely. The delay—from October 2018 to a launch window between March and June 2019—was primarily caused by components of JWST's spacecraft taking longer to integrate than planned. JWST made considerable progress toward the completion of integration and test activities in the past year. However, the project used all remaining schedule reserve—or extra time set aside in the schedule in the event of delays or unforeseen risks—to address technical issues, including an anomaly on the telescope found during vibration testing. Extending the launch window provided the project up to 4 months of schedule reserve. However, shortly after requesting the new launch window in September 2017, the project determined that several months of schedule reserve would be needed to address lessons learned from the initial folding and deployment of the observatory's sunshield (see image). Given remaining integration and test work ahead—the phase in development where problems are most likely to be found and schedules tend to slip—coupled with only 1.5 months of schedule reserves remaining to the end of the launch window, additional launch delays are likely. The project's Standing Review Board will conduct an independent review of JWST's schedule status in early 2018 to determine if the June 2019 launch window can be met.

View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart

JWST, a large, deployable telescope intended to be the successor to the Hubble Space Telescope, is one of NASA's most complex and expensive projects, at an anticipated cost of $8.8 billion. Congress set an $8 billion JWST development cost cap in 2011, and the remaining $837 million is for its operations costs. JWST is intended to revolutionize our understanding of star and planet formation and advance the search for the origins of our universe. With significant integration and testing planned for the remaining period until launch, the JWST project will still need to address many challenges during the remainder of integration and testing.

In 2017, the National Aeronautics and Space Administration's (NASA) James Webb Space Telescope (JWST) project delayed its launch readiness date by at least 5 months, and further delays are likely. The delay—from October 2018 to a launch window between March and June 2019—was primarily caused by components of JWST's spacecraft taking longer to integrate than planned. JWST made considerable progress toward the completion of integration and test activities in the past year. However, the project used all remaining schedule reserve—or extra time set aside in the schedule in the event of delays or unforeseen risks—to address technical issues, including an anomaly on the telescope found during vibration testing. Extending the launch window provided the project up to 4 months of schedule reserve. However, shortly after requesting the new launch window in September 2017, the project determined that several months of schedule reserve would be needed to address lessons learned from the initial folding and deployment of the observatory's sunshield (see image). Given remaining integration and test work ahead—the phase in development where problems are most likely to be found and schedules tend to slip—coupled with only 1.5 months of schedule reserves remaining to the end of the launch window, additional launch delays are likely. The project's Standing Review Board will conduct an independent review of JWST's schedule status in early 2018 to determine if the June 2019 launch window can be met.

More books from Progressive Management

Cover of the book 21st Century FEMA Study Course: Mitigation eGrants for the Grant Applicant (IS-31) by Progressive Management
Cover of the book 21st Century U.S. Military Documents: Air Force Intelligence - Force Protection (FP), Predictive Battlespace Awareness (PBA), Open Source Intelligence (OSINT), ISR, Contingency Unit by Progressive Management
Cover of the book 2013 China Military and Security Report: People's Liberation Army (PLA), Space, Cyber Attacks on American Military, Technology, People's Republic of China Force Modernization, Taiwan by Progressive Management
Cover of the book 21st Century U.S. Military Manuals: Combat Net Radio Operations (FM 11-32) SINCGARS, Battlefield Radio (Value-Added Professional Format Series) by Progressive Management
Cover of the book Art of War Paper: Operations at the Border - Efforts to Disrupt Insurgent Safe-Havens, Dhofar, Oman, Insurgency, Counterinsurgency by Progressive Management
Cover of the book Competing Claims Among Argentina, Chile, and Great Britain in the Antarctic: Economic and Geopolitical Undercurrents - Treaty, Geopolitical Perspectives, U.S. Interests, Falklands Malvinas Conflict by Progressive Management
Cover of the book Colombia in Perspective: Orientation Guide and Spanish Cultural Orientation: Geography, History, Economy, Society, Security, Military, Religion, Amazon, Bogota, Medellin, Cali, Narcotrafficking by Progressive Management
Cover of the book The Chain of Environmental Command: How a Club of Billionaires and Their Foundations Control the Environmental Movement and Obama's EPA: Anti-Fracking, Global Warming and Climate Change by Progressive Management
Cover of the book The Misuse of the Studies and Observation Group (SOG) as a National Asset in Vietnam - Management of the Unconventional War Effort in North Vietnam, Covert and Clandestine Operations by Progressive Management
Cover of the book National Guard Forces in the Cyber Domain: Integrating the Guard into National Cyber Forces and Defenses, Cybersecurity Protecting Critical Infrastructure from Hactivists and Terrorist Groups by Progressive Management
Cover of the book The American Military and the Far East: Ninth Military History Symposium - Asia and Asian Military, Objectives, Pacification, Japan Occupation, World War II, Vietnam, MacArthur, Orient Naval Strategy by Progressive Management
Cover of the book History of the Joint Chiefs of Staff: The War in Vietnam 1960-1968, Part 1 - Eisenhower and Kennedy, Laos, Communist Offensive, McNamara and the Buildup, Defoliation, Fall of Diem by Progressive Management
Cover of the book Complete Guide to the Buffalo Soldiers: History of Black Regiments After the Civil War, Western Cavalry and Indian Wars, Spanish-American War, African-American Troops Patrolling National Parks by Progressive Management
Cover of the book Army Engineers in New England 1775-1975: The Military and Civil Work of the Corps of Engineers in New England, Revolutionary War, George Washington, Dredging, Flood Protection, Boston Harbor by Progressive Management
Cover of the book 21st Century Peacekeeping and Stability Operations Institute (PKSOI) Papers - Known Unknowns: Unconventional "Strategic Shocks" in Defense Strategy Development by Progressive Management
We use our own "cookies" and third party cookies to improve services and to see statistical information. By using this website, you agree to our Privacy Policy