2018 Report on James Webb Space Telescope (JWST): Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap

Nonfiction, Science & Nature, Science, Physics, Astronomy, Astrophysics & Space Science
Cover of the book 2018 Report on James Webb Space Telescope (JWST): Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap by Progressive Management, Progressive Management
View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart
Author: Progressive Management ISBN: 9781370563555
Publisher: Progressive Management Publication: March 1, 2018
Imprint: Smashwords Edition Language: English
Author: Progressive Management
ISBN: 9781370563555
Publisher: Progressive Management
Publication: March 1, 2018
Imprint: Smashwords Edition
Language: English

JWST, a large, deployable telescope intended to be the successor to the Hubble Space Telescope, is one of NASA's most complex and expensive projects, at an anticipated cost of $8.8 billion. Congress set an $8 billion JWST development cost cap in 2011, and the remaining $837 million is for its operations costs. JWST is intended to revolutionize our understanding of star and planet formation and advance the search for the origins of our universe. With significant integration and testing planned for the remaining period until launch, the JWST project will still need to address many challenges during the remainder of integration and testing.

In 2017, the National Aeronautics and Space Administration's (NASA) James Webb Space Telescope (JWST) project delayed its launch readiness date by at least 5 months, and further delays are likely. The delay—from October 2018 to a launch window between March and June 2019—was primarily caused by components of JWST's spacecraft taking longer to integrate than planned. JWST made considerable progress toward the completion of integration and test activities in the past year. However, the project used all remaining schedule reserve—or extra time set aside in the schedule in the event of delays or unforeseen risks—to address technical issues, including an anomaly on the telescope found during vibration testing. Extending the launch window provided the project up to 4 months of schedule reserve. However, shortly after requesting the new launch window in September 2017, the project determined that several months of schedule reserve would be needed to address lessons learned from the initial folding and deployment of the observatory's sunshield (see image). Given remaining integration and test work ahead—the phase in development where problems are most likely to be found and schedules tend to slip—coupled with only 1.5 months of schedule reserves remaining to the end of the launch window, additional launch delays are likely. The project's Standing Review Board will conduct an independent review of JWST's schedule status in early 2018 to determine if the June 2019 launch window can be met.

View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart

JWST, a large, deployable telescope intended to be the successor to the Hubble Space Telescope, is one of NASA's most complex and expensive projects, at an anticipated cost of $8.8 billion. Congress set an $8 billion JWST development cost cap in 2011, and the remaining $837 million is for its operations costs. JWST is intended to revolutionize our understanding of star and planet formation and advance the search for the origins of our universe. With significant integration and testing planned for the remaining period until launch, the JWST project will still need to address many challenges during the remainder of integration and testing.

In 2017, the National Aeronautics and Space Administration's (NASA) James Webb Space Telescope (JWST) project delayed its launch readiness date by at least 5 months, and further delays are likely. The delay—from October 2018 to a launch window between March and June 2019—was primarily caused by components of JWST's spacecraft taking longer to integrate than planned. JWST made considerable progress toward the completion of integration and test activities in the past year. However, the project used all remaining schedule reserve—or extra time set aside in the schedule in the event of delays or unforeseen risks—to address technical issues, including an anomaly on the telescope found during vibration testing. Extending the launch window provided the project up to 4 months of schedule reserve. However, shortly after requesting the new launch window in September 2017, the project determined that several months of schedule reserve would be needed to address lessons learned from the initial folding and deployment of the observatory's sunshield (see image). Given remaining integration and test work ahead—the phase in development where problems are most likely to be found and schedules tend to slip—coupled with only 1.5 months of schedule reserves remaining to the end of the launch window, additional launch delays are likely. The project's Standing Review Board will conduct an independent review of JWST's schedule status in early 2018 to determine if the June 2019 launch window can be met.

More books from Progressive Management

Cover of the book Facing Uncertainty: The Role of the M1 Abrams Tank in U.S. Army of 2015-2025 - Hybrid Threats and Combined Arms Maneuver, Case Study of Israel Merkava Tank in Operations Cast Lead and Protective Edge by Progressive Management
Cover of the book National Defense Intelligence College Paper: A Muslim Archipelago: Islam and Politics in Southeast Asia - Islam in Malaysia, Thailand, Indonesia by Progressive Management
Cover of the book Pathbreakers: U.S. Marine African American Officers in Their Own Words - Oral History Anthology with 21 Personal Accounts Covering 60 Years of Service - NASA Administrator Charles Bolden, Jr. by Progressive Management
Cover of the book United States Earthquake Early Warning System: How Theory and Analysis Can Save America Before the Big One Happens - Advocating Implementation of the ShakeAlert Warning System on the Seismic Network by Progressive Management
Cover of the book Responsibility of Command: How UN and NATO Commanders Influenced Airpower over Bosnia - History of the Bosnia War, Operation Deny Flight, Srebrenica by Progressive Management
Cover of the book 21st Century U.S. Military Manuals: Ranger Unit Operations - FM 7-85 (Value-Added Professional Format Series) by Progressive Management
Cover of the book Encyclopedia of NASA Lessons Learned (Part 3): Thousands of Aerospace Technology Engineering Reports, Problems, Accidents, Mishaps, Ideas and Solutions - Space Shuttle, Spacecraft, Rockets, Aircraft by Progressive Management
Cover of the book The United States Air Force (USAF): Basic Documents on Roles and Missions (Air Staff Historical Study) - McNamara, Curtis LeMay, James Forrestal, Space Command, Key West Agreement by Progressive Management
Cover of the book 21st Century U.S. Military Manuals: Information Operations Field Manual - FM 100-6 by Progressive Management
Cover of the book Understanding and Managing North Korea's Nuclear Ambitions: DPRK Regime Survival, Use as Deterrence, Leverage, Prestige, Great Power Status, New Approaches to the Rogue State, Kim Family by Progressive Management
Cover of the book Czech Republic in Perspective: Orientation Guide and Cultural Orientation: Geography, History, Economy, Security, Religion, Prague, Praha, Brno, Communism, Velvet Revolution, Elbe River by Progressive Management
Cover of the book 21st Century U.S. Military Manuals: U.S. Marine Corps (USMC) Leading Marines - Marine Corps Warfighting Publication (MCWP) 6-11 by Progressive Management
Cover of the book Fort Leavenworth: The People Behind the Names: People Who Have Left Their Mark on the Dowager Queen of Frontier Forts – Fort History, Geography, Buildings, Stained Glass Windows, Streets and Trails by Progressive Management
Cover of the book Augmenting Our Influence: Alliance Revitalization and Partner Development - U.S. Strategic Interests in Asia-Pacific, Senkaku, Obama Strategy, Europe, NATO, Future of American Landpower by Progressive Management
Cover of the book Are We Prepared? Four WMD Crises That Could Transform U.S. Security: Failed WMD-armed State, Collapse of Nonproliferation Regime, Biological Terror Campaign, Nuclear Detonation in American City by Progressive Management
We use our own "cookies" and third party cookies to improve services and to see statistical information. By using this website, you agree to our Privacy Policy