2018 Report on James Webb Space Telescope (JWST): Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap

Nonfiction, Science & Nature, Science, Physics, Astronomy, Astrophysics & Space Science
Cover of the book 2018 Report on James Webb Space Telescope (JWST): Integration and Test Challenges Have Delayed Launch and Threaten to Push Costs Over Cap by Progressive Management, Progressive Management
View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart
Author: Progressive Management ISBN: 9781370563555
Publisher: Progressive Management Publication: March 1, 2018
Imprint: Smashwords Edition Language: English
Author: Progressive Management
ISBN: 9781370563555
Publisher: Progressive Management
Publication: March 1, 2018
Imprint: Smashwords Edition
Language: English

JWST, a large, deployable telescope intended to be the successor to the Hubble Space Telescope, is one of NASA's most complex and expensive projects, at an anticipated cost of $8.8 billion. Congress set an $8 billion JWST development cost cap in 2011, and the remaining $837 million is for its operations costs. JWST is intended to revolutionize our understanding of star and planet formation and advance the search for the origins of our universe. With significant integration and testing planned for the remaining period until launch, the JWST project will still need to address many challenges during the remainder of integration and testing.

In 2017, the National Aeronautics and Space Administration's (NASA) James Webb Space Telescope (JWST) project delayed its launch readiness date by at least 5 months, and further delays are likely. The delay—from October 2018 to a launch window between March and June 2019—was primarily caused by components of JWST's spacecraft taking longer to integrate than planned. JWST made considerable progress toward the completion of integration and test activities in the past year. However, the project used all remaining schedule reserve—or extra time set aside in the schedule in the event of delays or unforeseen risks—to address technical issues, including an anomaly on the telescope found during vibration testing. Extending the launch window provided the project up to 4 months of schedule reserve. However, shortly after requesting the new launch window in September 2017, the project determined that several months of schedule reserve would be needed to address lessons learned from the initial folding and deployment of the observatory's sunshield (see image). Given remaining integration and test work ahead—the phase in development where problems are most likely to be found and schedules tend to slip—coupled with only 1.5 months of schedule reserves remaining to the end of the launch window, additional launch delays are likely. The project's Standing Review Board will conduct an independent review of JWST's schedule status in early 2018 to determine if the June 2019 launch window can be met.

View on Amazon View on AbeBooks View on Kobo View on B.Depository View on eBay View on Walmart

JWST, a large, deployable telescope intended to be the successor to the Hubble Space Telescope, is one of NASA's most complex and expensive projects, at an anticipated cost of $8.8 billion. Congress set an $8 billion JWST development cost cap in 2011, and the remaining $837 million is for its operations costs. JWST is intended to revolutionize our understanding of star and planet formation and advance the search for the origins of our universe. With significant integration and testing planned for the remaining period until launch, the JWST project will still need to address many challenges during the remainder of integration and testing.

In 2017, the National Aeronautics and Space Administration's (NASA) James Webb Space Telescope (JWST) project delayed its launch readiness date by at least 5 months, and further delays are likely. The delay—from October 2018 to a launch window between March and June 2019—was primarily caused by components of JWST's spacecraft taking longer to integrate than planned. JWST made considerable progress toward the completion of integration and test activities in the past year. However, the project used all remaining schedule reserve—or extra time set aside in the schedule in the event of delays or unforeseen risks—to address technical issues, including an anomaly on the telescope found during vibration testing. Extending the launch window provided the project up to 4 months of schedule reserve. However, shortly after requesting the new launch window in September 2017, the project determined that several months of schedule reserve would be needed to address lessons learned from the initial folding and deployment of the observatory's sunshield (see image). Given remaining integration and test work ahead—the phase in development where problems are most likely to be found and schedules tend to slip—coupled with only 1.5 months of schedule reserves remaining to the end of the launch window, additional launch delays are likely. The project's Standing Review Board will conduct an independent review of JWST's schedule status in early 2018 to determine if the June 2019 launch window can be met.

More books from Progressive Management

Cover of the book The Sources of Protracted Conflict in the Western Sahara: Algerian Hegemony, Spanish Decolonization, Ceasefire, UN Problems, Algeria and Polisario Front, SADR, Tindouf Region, Morocco, ISIS, al-Qaeda by Progressive Management
Cover of the book 21st Century Peacekeeping and Stability Operations Institute (PKSOI) Papers - Social Capital, Policing and the Rule-of-Law: Keys to Stabilization, Military Police - Prisons, Iraq, Afghanistan by Progressive Management
Cover of the book Climate Change and Global Warming Encyclopedia: Sweeping Coverage of All Aspects of Carbon Dioxide and Greenhouse Gases, Sea Levels, Ecosystems, Computer Models, Extreme Weather, Energy and Carbon by Progressive Management
Cover of the book Protecting America: Cold War Defensive Sites - Concise History of the Cold War and U.S. Military Sites, Extensive Bibliography and Source Information - Nuclear Weapons, Missiles by Progressive Management
Cover of the book 21st Century U.S. Military Manuals: Public Affairs Operations Field Manual - FM 46-1 (Value-Added Professional Format Series) by Progressive Management
Cover of the book They Made it Happen: Oral Histories of the Unsung Heroes of NASA's Space Shuttle Program - Engineers and Managers Recount Amazing Stories about America's Winged Space Marvel by Progressive Management
Cover of the book Federal Bureau of Investigation (FBI) Handbook of Forensic Services, 2007 Edition - Crime Scene Forensics and Criminal Evidence Collection and Handling Procedures by Progressive Management
Cover of the book First Responder Refresher: National Standard Curriculum Instructor Course Guide - Airway, Circulation, Illness and Injury, Childbirth and Children, EMS Operations by Progressive Management
Cover of the book 2012 Biomass Multi-Year Program Plan: Biofuels, Bioproducts, and Biopower - Conversion Technologies, Feedstock Supply, Bio-Oil Pathways, Bioenergy Supply Chain by Progressive Management
Cover of the book Going to Extremes: Climate Change and the Increasing Risk of Weather Disasters by Progressive Management
Cover of the book Social Media: New Spaces for Contention in Authoritarian Systems - Case Study of Bahrain, Arab Spring, Islamic Sectarian Violence, Protest Movements, Twitter, Facebook, YouTube, Blogging by Progressive Management
Cover of the book Controlling the Population: A Study of the Civilian Irregular Defense Group - Counterinsurgency, Vietnam, Mobile Strike Forces, Strategic Hamlet Program, Viet Cong, North Vietnamese Army by Progressive Management
Cover of the book 2011 Essential Guide to Hurricane Survival, Safety, and Preparedness: Practical Emergency Plans and Protective Measures, Plus Complete Information on Hurricanes and Tropical Storms by Progressive Management
Cover of the book The Spanish Civil War: Failure at the Strategic Level - Report on the Dress Rehearsal for World War II, Franco and Hitler, Relationships Between Spain, Britain, France, USSR, U.S., Germany, and Italy by Progressive Management
Cover of the book 2012 Republican Vice Presidential Candidate Paul Ryan: Issue Statements, Speeches, Thoughts and Policies, Complete Path to Prosperity Federal Budget Plans with Proposed Changes to Medicare and Taxes by Progressive Management
We use our own "cookies" and third party cookies to improve services and to see statistical information. By using this website, you agree to our Privacy Policy